Violation Detail
Standard Cited: 19100303 B01 General.
This violation item has been deleted.
Inspection Nr: 109779.015
Citation: 01007A
Citation Type: Serious
Abatement Date: 03/27/2012
Initial Penalty: $7,000.00
Current Penalty: $0.00
Issuance Date: 03/22/2012
Nr Instances: 1
Nr Exposed: 5
Related Event Code (REC):
Gravity: 10
Report ID: 0830600
Contest Date: 04/12/2012
Final Order: 01/09/2013
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 01/09/2013 | $0.00 | 03/27/2012 | Serious | |
Penalty | C: Contested | 04/16/2012 | $7,000.00 | 03/27/2012 | Serious | |
Penalty | Z: Issued | 03/22/2012 | $7,000.00 | 03/27/2012 | Serious |
Text For Citation: 01 Item/Group: 007A Hazard:
29 CFR 1910.303(b)(1): Electrical equipment was not free from recognized hazards that were likely to cause death or serious physical harm to employees: a) On or about October 29, 2011, and at times prior, Continental Resources, Inc., as the controlling employer, did not ensure that Cyclone Drilling, Inc., a subcontractor, protected their employees from electrical hazards. The electrical systems were not examined, using the criteria of sections (i) through (viii) or 29 CFR 1910.303(b)(1) to assure they were free from recognized hazards.