Violation Detail
Standard Cited: 19100217 F02 Mechanical power presses.
Inspection Nr: 1051184.015
Citation: 01010
Citation Type: Serious
Abatement Date: 03/31/2016 2
Initial Penalty: $7,000.00
Current Penalty: $5,250.00
Issuance Date: 09/30/2015
Nr Instances: 14
Nr Exposed: 40
Related Event Code (REC):
Gravity: 10
Report ID: 0524530
Contest Date: 10/27/2015
Final Order: 05/31/2016
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 05/31/2016 | $5,250.00 | 03/31/2016 | Serious | |
Penalty | C: Contested | 11/02/2015 | $7,000.00 | 10/27/2015 | Serious | |
Penalty | Z: Issued | 09/30/2015 | $7,000.00 | 10/27/2015 | Serious |
Text For Citation: 01 Item/Group: 010 Hazard:
29 CFR 1910.217(f)(2): Supervision to ensure that correct operating procedures were being followed on mechanical power press(es) was inadequate: The following mechanical power press controls were not adequately supervised. The keys were left in the controls of the following presses in the Shot Tower/Swager Area: A. Press #11 B. Press #4 C. Press #31 D. Press #6 E. Press #7 F. Press #9 G. Press #10 H. Press #34 I. Press #36 J. Press #39 K. Press #35 L. Press #38 M. Press #33 N. Press #37