Violation Detail
Standard Cited: 19100305 G01 IV C Wiring methods, components, and equipment for general use.
Inspection Nr: 1050814.015
Citation: 01006B
Citation Type: Serious
Abatement Date: 10/13/2015 2
Initial Penalty: $3,600.00
Current Penalty: $0.00
Issuance Date: 09/28/2015
Nr Instances: 1
Nr Exposed: 5
Related Event Code (REC):
Gravity: 5
Report ID: 0523100
Contest Date:
Final Order: 10/19/2015
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 10/19/2015 | $0.00 | 10/13/2015 | Serious | |
Penalty | Z: Issued | 09/28/2015 | $3,600.00 | 10/13/2015 | Serious |
Text For Citation: 01 Item/Group: 006B Hazard:
29 CFR 1910.305(g)(1)(iv)(C): Flexible cords and cables were used where run through doorways, windows, or similar openings. (a) On or about March 31, 2015, on the argon platform, the employer did not ensure employees were not exposed to an electrical hazard due to a flexible electrical cord being ran through a hole in the building. Employees were exposed to electrical hazards.