Violation Detail
Standard Cited: 19100147 C04 II The control of hazardous energy (lockout/tagout).
Inspection Nr: 1020611.015
Citation: 01003
Citation Type: Serious
Abatement Date: 08/06/2015 2
Initial Penalty: $7,000.00
Current Penalty: $7,000.00
Issuance Date: 07/13/2015
Nr Instances: 1
Nr Exposed: 6
Related Event Code (REC): A
Gravity: 10
Report ID: 0418400
Contest Date:
Final Order: 07/10/2015
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | Z: Issued | 07/13/2015 | $7,000.00 | 08/06/2015 | Serious | |
Penalty | I: Informal Settlement | 07/10/2015 | $7,000.00 | 08/06/2015 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1910.147(c)(4)(ii): The energy control procedures did not clearly and specifically outline the scope, purpose, authorization, rules, and techniques to be utilized for the control of hazardous energy, including, but not limited to Items of this section. (a) Planner Mill, Itipack Systems, SKP-25-1 Automated Heavy-Duty Strapping System, on or about and at times preceding to January 23, 2015, the company's energy control procedures did not specifically outline the rules and techniques to be utilized to obtain a zero energy state when making adjustments to the plastic strap feeding mechanism that bands the lumber bundles for shipment.