Violation Detail
Standard Cited: 19100254 D09 I Arc welding and cutting.
Inspection Nr: 1018261.015
Citation: 02001
Citation Type: Other
Abatement Date: 3
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 07/10/2015
Nr Instances: 2
Nr Exposed: 3
Related Event Code (REC):
Gravity:
Report ID: 0112000
Contest Date:
Final Order: 07/30/2015
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 07/30/2015 | $0.00 | Other | ||
Penalty | Z: Issued | 07/10/2015 | $0.00 | Other |
Text For Citation: 02 Item/Group: 001 Hazard:
29 CFR 1910.254(d)(9)(i): The use of the equipment was not discontinued until safety has been assured: On, or about, February 13, 2015, in the following locations, the insulation provided on electrode holders for arc welding equipment had eroded, exposing bare metal parts: A. Building 68, Furnace area, Miller stick welder. B. Building 34, Maintenance Shop, Hobart stick welder