Standard Cited: 19100303 A General.
Inspection Nr: 1017962.015
Citation: 01001A
Citation Type: Serious
Abatement Date: 1
Initial Penalty: $3,740.00
Current Penalty: $5,500.00
Issuance Date: 03/23/2015
Nr Instances: 1
Nr Exposed: 20
Related Event Code (REC):
Gravity: 5
Report ID: 0524200
Contest Date: 04/16/2015
Final Order: 02/19/2016
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 02/19/2016 | $5,500.00 | Serious | ||
Penalty | C: Contested | 04/16/2015 | $3,740.00 | Serious | ||
Penalty | Z: Issued | 03/23/2015 | $3,740.00 | Serious |
Text For Citation: 01 Item/Group: 001A Hazard:
29 CFR 1910.303(a): The conductors and/or equipment required or permitted by this subpart were not approved: a) Carrier Case 85 - The employer failed to ensure that all pieces of electrical equipment, such as the orange extension cord with multiple power taps, were accepted, or certified, or listed, or labeled, or otherwise determined to be safe by a nationally recognized testing laboratory. No abatement certification or documentation is required for this item.