Violation Detail
Standard Cited: 19100269 O03 IV Electric Power Generation, Transmission, and Distribution.
Inspection Nr: 1003042.015
Citation: 03001
Citation Type: Other
Abatement Date: 11/30/2015 2
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 04/10/2015
Nr Instances: 2
Nr Exposed: 3
Related Event Code (REC):
Gravity:
Report ID: 0419700
Contest Date:
Final Order: 05/07/2015
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 05/07/2015 | $0.00 | 11/30/2015 | Other | |
Penalty | Z: Issued | 04/10/2015 | $0.00 | 05/28/2015 | Other |
Text For Citation: 03 Item/Group: 001 Hazard:
29 CFR 1910.269(o)(3)(iv): Guarding was not provided within test areas to control access to test equipment or to apparatus under test that may become energized as part of the testing by either direct or inductive coupling, in order to prevent accidental employee contact with energized parts: a. On or about October 13, 2014, at the Reddick Substation, during Doble Testing, the test area was not barricaded to control access to the test equipment and transformer, exposing employees to an electrocution hazard by accidental contact with energized electrical parts that were conducting 10 Kilovolts and 300 milliamps. b. On or about October 15, 2014, at the Reddick Substation, during Doble Testing, the test area was not barricaded to control access to the test equipment and transformer, exposing employees to an electrocution hazard by accidental contact with energized electrical parts that were conducting 10 Kilovolts and 300 milliamps.