Violation Detail
Standard Cited: 19100269 O04 V Electric Power Generation, Transmission, and Distribution.
Inspection Nr: 1003042.015
Citation: 01003
Citation Type: Serious
Abatement Date: 08/31/2015 2
Initial Penalty: $3,000.00
Current Penalty: $7,000.00
Issuance Date: 04/10/2015
Nr Instances: 2
Nr Exposed: 2
Related Event Code (REC):
Gravity: 1
Report ID: 0419700
Contest Date:
Final Order: 05/07/2015
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 05/07/2015 | $7,000.00 | 08/31/2015 | Serious | |
Penalty | Z: Issued | 04/10/2015 | $3,000.00 | 05/06/2015 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1910.269(o)(4)(v): A ground was not placed on the high-voltage terminal and other exposed terminals when the test area was entered after equipment was deenergized: a. On or about October 13, 2014, at the Reddick Florida substation, in the Doble test area, the bushing terminals of the number 2 transformer were not grounded between test runs, exposing the Test Operator Assistant to an electric shock hazard when working in the test area. b. On or about October 15, 2014, at the Reddick Florida substation, in the Doble test area, the bushing terminals of the number 2 transformer were not grounded between test runs, exposing the Test Operator Assistant to an electric shock hazard when working in the test area.