Standard Cited: 19260850 A Preparatory operations.
Inspection Nr: 1240883.015
Citation: 02001
Citation Type: Other
Abatement Status: Not Completed - AD Discretion
Initial Penalty: $305.00
Current Penalty: $305.00
Issuance Date: 09/01/2017
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 09/08/2017
Gravity:
Report ID: 0523400
Contest Date:
Final Order: 10/23/2017
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | Z: Issued | 09/01/2017 | $305.00 | 09/08/2017 | Other |
Text For Citation: 02 Item/Group: 001 Hazard:
29 CFR 1926.850(a): An engineering survey was not performed by a competent person to determine the conditions of the framing floors and walls and the possibility of unplanned collapse of any portion of the structure prior to permitting employees to start demolition operations. (a) The employer did not ensure that an engineering survey was conducted prior to allowing employees conduct demolition operations.