Standard Cited: 19100119 F03 Process safety management of highly hazardous chemicals.

Inspection Nr: 1213761.015

Citation: 01008

Citation Type: Serious

Abatement Status: Abatement Completed

Initial Penalty: $7,967.00

Current Penalty: $4,780.20

Issuance Date: 08/23/2017

Nr Instances: 5

Nr Exposed: 5

Abatement Date: 12/31/2017

Gravity: 5

Report ID: 0729700

Contest Date:

Final Order: 09/14/2017

Related Event Code (REC):

Emphasis:


Penalty and Failure to Abate Event History
Type Latest Event Event Date Penalty Abatement Due Date Citation Type Failure to Abate Inspection
Penalty I: Informal Settlement 09/14/2017 $4,780.20 12/31/2017 Serious  
Penalty Z: Issued 08/23/2017 $7,967.00 09/19/2017 Serious  

Text For Citation: 01 Item/Group: 008 Hazard:

29 CFR 1910.119(f)(3): The operating procedures were not reviewed as often as necessary to assure that they reflect current operating practice, including changes that result from changes in process chemicals, technology, and equipment, and changes to facilities. The employer did not certify annually that these operating procedures were current and accurate: Employees engaged in operating, inspecting, testing, and maintaining activities at the covered process equipment in the roof top, the CP-2 and CP-4 engine rooms were exposed to catastrophic release of ammonia which results in asphyxiation, explosion and flash fire leading to death and injury to persons in and near the facility in that the current written operating procedures for the Ammonia process equipment including but not limited to the following were not reviewed and certified annually to assure that they reflected current and accurate operating practice. Identified operating procedures such as but not limited to the following: a) Binder 2 - OP: Screw Compressor CP-2 / C-18 / K12841 b) Binder 2 - OP: Screw Compressor K12846 / B-16 CP-2 c) Binder 2 - OP: Screw Compressor K12847 / B-17 CP-2 d) Binder 8 - OP: Pump 1 +10 Accumulator (RP1+10) - CP-4 PUMP1, +10 Accumulator/Intercooler - P14822 RP1+10 SOUTH PUMP e) Binder 8 - OP: Pump 1 +10 Accumulator (RP1+10) - CP-4 PUMP, +10 Accumulator - P14824 RP1+10 NORTH PUMP 29 CFR 1903.19(c)(1) requires certification that the abatement of the above violations is complete.

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.