Violation Detail
Standard Cited: 19100146 J06 Permit-required confined spaces
Inspection Nr: 312622178
Citation: 01006D
Citation Type: Serious
Abatement Status: X
Initial Penalty:
Current Penalty:
Issuance Date: 01/13/2010
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 03/01/2010
Gravity: 10
Report ID: 0522300
Contest Date:
Final Order:
Related Event Code (REC): C
Emphasis:
Substance: 1340
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 02/03/2010 | 03/01/2010 | Serious | ||
| Penalty | Z: Issued | 01/13/2010 | 01/22/2010 | Serious |
Text For Citation: 01 Item/Group: 006D Hazard: REFINERY
29 CFR 1910.146(j)(6): The employer did not ensure that each entry supervisor determined, whenever responsibility for a permit space entry operation was transferred and at intervals dictated by the hazards and operations performed within the space, that entry operations remained consistent with terms of the entry permit and that acceptable entry conditions were maintained: Employees entered tank 242 under a confined space permit to perform maintenance and cleaning; the maintenance work was not noted on the permit and the permit did not note that employees would be working above the floating roof where they could not be seen by the attendant.