Violation Detail
Standard Cited: 19100147 D02 The control of hazardous energy (lockout/tagout).
Inspection Nr: 1342021.015
Citation: 01006B
Citation Type: Serious
Abatement Date: 04/11/2019 2
Initial Penalty: $11,641.00
Current Penalty: $0.00
Issuance Date: 01/22/2019
Nr Instances: 1
Nr Exposed: 11
Related Event Code (REC): A
Gravity: 10
Report ID: 0626700
Contest Date:
Final Order: 02/07/2019
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 02/07/2019 | $0.00 | 04/11/2019 | Serious | |
Penalty | Z: Issued | 01/22/2019 | $11,641.00 | 03/11/2019 | Serious |
Text For Citation: 01 Item/Group: 006B Hazard:
29 CFR 1910.147(d)(2): An orderly shutdown of machine or equipment was not utilized to avoid any additional or increased hazards to employees as a result of equipment stoppage: a) At the facility, furnace area: On or about August 25, 2018, 1 Mega Watt arc furnaces were not de-energized when employees performed service and maintenance tasks such as but not limited to threading new lengths of electrodes. This condition exposed employees to an electrocution hazard.