Standard Cited: 19100147 D06 The control of hazardous energy (lockout/tagout).

Inspection Nr: 1067666.015

Citation: 01006

Citation Type: Serious

Abatement Status: Abatement Completed

Initial Penalty: $7,000.00

Current Penalty: $4,900.00

Issuance Date: 07/30/2015

Nr Instances: 1

Nr Exposed: 2

Abatement Date: 08/25/2015

Gravity: 10

Report ID: 0522300

Contest Date:

Final Order: 08/20/2015

Related Event Code (REC): R

Emphasis:


Penalty and Failure to Abate Event History
Type Latest Event Event Date Penalty Abatement Due Date Citation Type Failure to Abate Inspection
Penalty I: Informal Settlement 08/20/2015 $4,900.00 08/25/2015 Serious  
Penalty Z: Issued 07/30/2015 $7,000.00 08/25/2015 Serious  

Text For Citation: 01 Item/Group: 006 Hazard:

29 CFR 1910.147(d)(6): Prior to starting work on machines or equipment that had been locked out or tagged out, the authorized employee did not verify that isolation and deenergization of the machine or equipment had been accomplished: On or about May 27, 2015, the employer did not ensure prior to performing die changes, material changes, and the changing of punches inside the point of operation of a Niagara 50 ton, part revolution mechanical power press, Serial No. 30223, known as the Mini Line #4, authorized employees verified isolation and de-energiztion of the press had been accomplished.

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.