Powered by GoogleTranslate

Violation Detail

Standard Cited: 19100303 B01 General.

Inspection Nr: 1118961.015

Citation: 01002A

Citation Type: Serious

Abatement Status: Abatement Completed

Initial Penalty: $4,950.00

Current Penalty: $2,475.00

Issuance Date: 04/27/2016

Nr Instances: 1

Nr Exposed: 4

Abatement Date: 05/09/2016

Gravity: 5

Report ID: 0215800

Contest Date: 05/20/2016

Final Order: 04/03/2017

Related Event Code (REC):

Emphasis:


Penalty and Failure to Abate Event History
Type Latest Event Event Date Penalty Abatement Due Date Citation Type Failure to Abate Inspection
Penalty F: Formal Settlement 04/03/2017 $2,475.00 05/09/2016 Serious  
Penalty C: Contested 05/20/2016 $4,950.00 05/09/2016 Serious  
Penalty Z: Issued 04/27/2016 $4,950.00 05/09/2016 Serious  

Text For Citation: 01 Item/Group: 002A Hazard:

29 CFR 1910.303(b)(1): Electrical equipment was not free from recognized hazards that were likely to cause death or serious physical harm to employees: a) On or about 1/20/2016, Line #15 Area: The main power control box had a broken on/ off switch which had been bypassed. Abatement certification is required for this item.

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.

Close