Standard Cited: 19260451 B01 General requirements.
Inspection Nr: 967872.015
Citation: 01001
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $2,800.00
Current Penalty: $1,400.00
Issuance Date: 06/19/2014
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 07/16/2014
Gravity: 10
Report ID: 0418100
Contest Date:
Final Order: 07/08/2014
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection | 
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 07/08/2014 | $1,400.00 | 07/16/2014 | Serious | |
| Penalty | Z: Issued | 06/19/2014 | $2,800.00 | 07/16/2014 | Serious | 
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1926.451(b)(1): Each platform on all working levels of scaffolds was not fully planked or decked between the front uprights and the guardrail supports as specified in paragraphs 1926.451(b)(1)(i)-(ii): On or about April 7, 2014, employees were exposed to fall hazards of approximately 16-22 feet when they were working from a scaffold that was not fully decked. The scaffold was used to get to the building fascia and top of the columns in order to remove damaged wood. The employees were preparing the building for the painting vendor by scraping loose paint and removing/repairing/replacing damaged wood.