Standard Cited: 19260960 E03  

Inspection Nr: 1274499.015

Citation: 01001

Citation Type: Serious

Abatement Status: Abatement Completed

Initial Penalty: $0.00

Current Penalty: $12,934.00

Issuance Date: 04/26/2018

Nr Instances: 1

Nr Exposed: 2

Abatement Date: 05/15/2018

Gravity: 10

Report ID: 0317300

Contest Date: 05/15/2018

Final Order: 11/08/2019

Related Event Code (REC): A

Emphasis:


Penalty and Failure to Abate Event History
Type Latest Event Event Date Penalty Abatement Due Date Citation Type Failure to Abate Inspection
Penalty F: Formal Settlement 11/08/2019 $12,934.00 05/15/2018 Serious  
Penalty C: Contested 05/17/2018 $0.00 05/15/2018 Serious  
Penalty Z: Issued 04/26/2018 $0.00 05/15/2018 Serious  

Text For Citation: 01 Item/Group: 001 Hazard:

29 CFR 1926.962(f)(2): Oreder of removal. The employer did not ensure that an employee removed a grounding device from the line or equipment using a live-line tool before removing the ground end connection. a) Eagle Nest Landing Road, Townsend, DE- On October 28, 2017, a grounding device was removed from a structure while the grounding device was still connected to a conductor subject to induced voltage.

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.