Inspection Detail
Inspection: 313208423 - Seaver Construction, Inc.
Inspection Information - Office: Springfield Area Office
Site Address:
Seaver Construction, Inc.
100 Flint Rd
Charlton, MA 01507
Mailing Address:
57 Russell St 2nd Fl, Woburn, MA 01801
Union Status: NonUnion
SIC:1541
NAICS: 236210/Industrial Building Construction
Inspection Type: Planned
Scope: Partial
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 12/22/2010
Planning Guide: Safety-Construction
Emphasis: S:Commercial Constr
Case Closed: 03/30/2011
| Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
|---|---|---|---|---|---|---|
| Initial Violations | 1 | 1 | ||||
| Current Violations | 1 | 1 | ||||
| Initial Penalty | $3,300 | $0 | $0 | $0 | $0 | $3,300 |
| Current Penalty | $0 | $0 | $0 | $1,650 | $0 | $1,650 |
| FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
| # | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1. | 01001A | Other | 19260403 B02 | 01/11/2011 | 01/15/2011 | $1,650 | $3,300 | $0 | I - Informal Settlement | ||
| 2. | 01001B | Other | 19260405 A02 III | 01/11/2011 | 01/15/2011 | $0 | $0 | $0 | I - Informal Settlement |