Inspection Detail
Inspection: 312513021 - Construction Systems, Inc.
Inspection Information - Office: Va-E-Manassas (Regional Office)- Safety 0355114
Site Address:
Construction Systems, Inc.
5th And Main Street
Warrenton, VA 20186
Mailing Address:
7135 Auburn Mill Road, Warrenton, VA 20186
Union Status: NonUnion
SIC:1742
NAICS: 238310/Drywall and Insulation Contractors
Inspection Type: Planned
Scope: Partial
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 08/14/2008
Planning Guide: Safety-Construction
Emphasis: L:Scaffold, S:Construction
Case Closed: 02/18/2009
| Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
|---|---|---|---|---|---|---|
| Initial Violations | 5 | 1 | 6 | |||
| Current Violations | 5 | 1 | 6 | |||
| Initial Penalty | $5,250 | $0 | $0 | $0 | $0 | $5,250 |
| Current Penalty | $3,000 | $0 | $0 | $0 | $0 | $3,000 |
| FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
| # | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1. | 01001 | Serious | 19260451 B01 | 09/30/2008 | 10/03/2008 | $600 | $1,050 | $0 | I - Informal Settlement | ||
| 2. | 01002 | Serious | 19260451 B07 | 09/30/2008 | 10/03/2008 | $600 | $1,050 | $0 | I - Informal Settlement | ||
| 3. | 01003A | Serious | 19260451 C02 | 09/30/2008 | 10/03/2008 | $600 | $1,050 | $0 | I - Informal Settlement | ||
| 4. | 01003B | Serious | 19260451 C02 II | 09/30/2008 | 10/03/2008 | $0 | $0 | $0 | - | ||
| 5. | 01004 | Serious | 19260451 F03 | 09/30/2008 | 10/03/2008 | $600 | $1,050 | $0 | I - Informal Settlement | ||
| 6. | 01005A | Serious | 19260452 C03 | 09/30/2008 | 10/03/2008 | $600 | $1,050 | $0 | I - Informal Settlement | ||
| 7. | 01005B | Serious | 19260452 C04 | 09/30/2008 | 10/03/2008 | $0 | $0 | $0 | - | ||
| 8. | 02001 | Other | 19101200 E01 | 09/30/2008 | 11/02/2008 | $0 | $0 | $0 | - |