Inspection Detail
Inspection: 309868719 - Mccrory Building Co., Inc.
Inspection Information - Office: Birmingham Area Office
Site Address:
Mccrory Building Co., Inc.
Hwy 280
Chelsea, AL 35043
Mailing Address:
P. O. Drawer 1266, Birmingham, AL 35201
Union Status: NonUnion
SIC:1542
NAICS: 236220/Commercial and Institutional Building Construction
Inspection Type: Planned
Scope: Complete
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 04/26/2006
Planning Guide: Safety-Construction
Emphasis: L:Fall
Case Closed: 09/11/2007
| Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
|---|---|---|---|---|---|---|
| Initial Violations | 4 | 1 | 5 | |||
| Current Violations | 5 | 5 | ||||
| Initial Penalty | $17,500 | $0 | $17,500 | $0 | $0 | $35,000 |
| Current Penalty | $0 | $0 | $0 | $24,000 | $0 | $24,000 |
| FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
| # | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1. | 01001 | Other | 19260453 B02 V | 08/29/2006 | 09/01/2006 | $5,000 | $5,000 | $0 | 09/26/2006 | J - ALJ Decision | |
| 2. | 01002A | Other | 19260453 B02 IV | 08/29/2006 | 09/01/2006 | $5,000 | $5,000 | $0 | 09/26/2006 | J - ALJ Decision | |
| 3. | 01002B | Other | 19260453 B02 VI | 08/29/2006 | 09/01/2006 | $0 | $0 | $0 | 09/26/2006 | J - ALJ Decision | |
| 4. | 01003 | Other | 19260701 B | 08/29/2006 | 09/01/2006 | $5,000 | $5,000 | $0 | 09/26/2006 | J - ALJ Decision | |
| 5. | 01004 | Other | 19260760 A01 | 08/29/2006 | 09/01/2006 | $2,000 | $2,500 | $0 | 09/26/2006 | J - ALJ Decision | |
| 6. | 02001 | Other | 19260025 A | 08/29/2006 | 09/18/2006 | $7,000 | $17,500 | $0 | 09/26/2006 | J - ALJ Decision |