Inspection Detail
Inspection: 309857472 - Obr Construction Inc
Inspection Information - Office: Pr-E-Arecibo 0257210
Site Address:
Obr Construction Inc
Carretera 2 Km 28.3 Bo Espinoza
Vega Alta, PR 00692
Mailing Address:
Hc 01 Box 6121, Loiza, PR 00772
Union Status: NonUnion
SIC:1742
NAICS: 238310/Drywall and Insulation Contractors
Inspection Type: Prog Related
Scope: Complete
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 08/26/2010
Emphasis:
Case Closed: 12/08/2010
| Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
|---|---|---|---|---|---|---|
| Initial Violations | 8 | 1 | 9 | |||
| Current Violations | 8 | 1 | 9 | |||
| Initial Penalty | $15,600 | $0 | $0 | $500 | $0 | $16,100 |
| Current Penalty | $15,600 | $0 | $0 | $500 | $0 | $16,100 |
| FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
| # | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1. | 01001 | Serious | 19260020 B01 | 09/28/2010 | 10/08/2010 | $1,500 | $1,500 | $0 | - | ||
| 2. | 01002 | Serious | 19260021 B02 | 09/28/2010 | 10/08/2010 | $1,500 | $1,500 | $0 | - | ||
| 3. | 01003 | Serious | 19260451 C02 | 09/28/2010 | 10/04/2010 | $2,100 | $2,100 | $0 | - | ||
| 4. | 01004 | Serious | 19260451 F03 | 09/28/2010 | 10/04/2010 | $2,100 | $2,100 | $0 | - | ||
| 5. | 01005 | Serious | 19260451 G01 | 09/28/2010 | 10/04/2010 | $2,100 | $2,100 | $0 | - | ||
| 6. | 01006 | Serious | 19260451 G04 I | 09/28/2010 | 10/04/2010 | $2,100 | $2,100 | $0 | - | ||
| 7. | 01007 | Serious | 19260454 A | 09/28/2010 | 10/08/2010 | $2,100 | $2,100 | $0 | - | ||
| 8. | 01008 | Serious | 19260454 B | 09/28/2010 | 10/08/2010 | $2,100 | $2,100 | $0 | - | ||
| 9. | 02001 | Other | 6A0001 | 09/28/2010 | 10/08/2010 | $500 | $500 | $0 | - |