Inspection: 308655869 - Bascon Corporation
Inspection Information - Office: San Francisco Ro
Site Address:
Bascon Corporation
Auditorium Building Gcc
Mangilao, GU 96913
Mailing Address:
P.O. Box 21867, Barrigada, GU 96921
Union Status: NonUnion
SIC:1541
NAICS: 236220/Commercial and Institutional Building Construction
Inspection Type: Planned
Scope: Complete
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 03/31/2005
Planning Guide: Safety-Construction
Emphasis: L:Progcon, S:Amputations
Case Closed: 02/07/2006
| Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
|---|---|---|---|---|---|---|
| Initial Violations | 2 | 2 | ||||
| Current Violations | 2 | 2 | ||||
| Initial Penalty | $1,350 | $0 | $0 | $0 | $0 | $1,350 |
| Current Penalty | $1,350 | $0 | $0 | $0 | $0 | $1,350 |
| FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
| # | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1. | 01001 | Serious | 5A0001 | 06/24/2005 | 07/26/2005 | $675 | $675 | $0 | - | ||
| 2. | 01002A | Serious | 19260602 A02 I | 06/24/2005 | 07/19/2005 | $675 | $675 | $0 | - | ||
| 3. | 01002B | Serious | 19260602 A09 I | 06/24/2005 | 07/19/2005 | $0 | $0 | $0 | - | ||
| 4. | 01002C | Serious | 19260602 A09 II | 06/24/2005 | 07/19/2005 | $0 | $0 | $0 | - |