Inspection Detail
Inspection: 302071089 - Avedon Engineering, Inc.
Inspection Information - Office: Denver Area Office
Site Address:
Avedon Engineering, Inc.
711 & 811 S. Lincoln Street
Longmont, CO 80501
Mailing Address:
P. O. Box 1018, Longmont, CO 80502
Union Status: NonUnion
SIC:3089
NAICS: 0
Inspection Type: Planned
Scope: Complete
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 11/18/1998
Planning Guide: Safety-Manufacturing
Emphasis: S:Amputations, N:Gsintarg
Case Closed: 12/17/1998
| Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
|---|---|---|---|---|---|---|
| Initial Violations | 2 | 1 | 3 | |||
| Current Violations | 2 | 1 | 3 | |||
| Initial Penalty | $1,650 | $0 | $0 | $0 | $0 | $1,650 |
| Current Penalty | $990 | $0 | $0 | $0 | $0 | $990 |
| FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
| # | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1. | 01001 | Serious | 19100023 A02 | 11/20/1998 | 11/27/1998 | $495 | $825 | $0 | I - Informal Settlement | ||
| 2. | 01002 | Serious | 19100212 A01 | 11/20/1998 | 11/27/1998 | $495 | $825 | $0 | I - Informal Settlement | ||
| 3. | 02001 | Other | 19100178 P01 | 11/20/1998 | 11/27/1998 | $0 | $0 | $0 | I - Informal Settlement |