Inspection Detail
Inspection: 1611278.015 - Benton-Georgia, Llc
Inspection Information - Office: San Antonio Area Office
Site Address:
Benton-Georgia, Llc
Galm Road-Phase Iii Road Project -Trench Near Station 165+15 Galm And Fm 471 (Culebra Rd) Extending 1.62 Miles North To Government Canyon State Park.
Helotes, TX 78023
Mailing Address:
P.O. Box 838, Douglasville, GA 30133
Union Status: NonUnion
SIC:
NAICS: 237120/Oil and Gas Pipeline and Related Structures Construction
Inspection Type: Planned
Scope: Partial
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 07/29/2022
Emphasis: P:Trench, N:Trench, L:Constr6, L:Hotdays
Case Closed: 02/02/2024
Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
---|---|---|---|---|---|---|
Initial Violations | 4 | 4 | ||||
Current Violations | 1 | 1 | ||||
Initial Penalty | $51,795 | $0 | $0 | $0 | $0 | $51,795 |
Current Penalty | $14,502 | $0 | $0 | $0 | $0 | $14,502 |
FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
# | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
---|---|---|---|---|---|---|---|---|---|---|---|
1. | 01001 | Serious | 19260300 B01 | 09/16/2022 | 10/06/2022 | $14,502 | $12,431 | $0 | 10/05/2022 | F - Formal Settlement | |
2. | 01002 | Serious | 19260652 A02 | 09/16/2022 | $0 | $10,360 | $0 | 10/05/2022 | F - Formal Settlement | Citation has been deleted. | |
3. | 01003 | Serious | 19260652 G01 II | 09/16/2022 | $0 | $14,502 | $0 | 10/05/2022 | F - Formal Settlement | Citation has been deleted. | |
4. | 01004 | Serious | 19260652 G02 | 09/16/2022 | $0 | $14,502 | $0 | 10/05/2022 | F - Formal Settlement | Citation has been deleted. |