Inspection Detail
Inspection: 1297887.015 - El Paso Underground Construction
Inspection Information - Office: El Paso Area Office
Site Address:
El Paso Underground Construction
200 Yards West Of Intersection Of Northen Pass And Resler
El Paso, TX 79911
Mailing Address:
1014 Cedar Street, El Paso, TX 79903
Union Status: NonUnion
SIC:
NAICS: 237110/Water and Sewer Line and Related Structures Construction
Inspection Type: Planned
Scope: Complete
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 02/27/2018
Emphasis: P:Trench, N:Trench
Case Closed: 02/08/2023
Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
---|---|---|---|---|---|---|
Initial Violations | 2 | 2 | 4 | |||
Current Violations | 1 | 1 | 2 | |||
Initial Penalty | $19,918 | $170,724 | $0 | $0 | $0 | $190,642 |
Current Penalty | $10,000 | $0 | $85,362 | $0 | $0 | $95,362 |
FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
# | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
---|---|---|---|---|---|---|---|---|---|---|---|
1. | 01001A | Serious | 19260021 B02 | 08/06/2018 | 12/24/2019 | $10,000 | $9,959 | $0 | 08/24/2018 | F - Formal Settlement | |
2. | 01001B | Serious | 19260651 J02 | 08/06/2018 | 12/24/2019 | $0 | $9,959 | $0 | 08/24/2018 | F - Formal Settlement | |
3. | 02001A | Repeat | 19260651 C02 | 08/06/2018 | 12/24/2019 | $85,362 | $85,362 | $0 | 08/24/2018 | F - Formal Settlement | |
4. | 02001B | Willful | 19260652 A01 | 08/06/2018 | 12/24/2019 | $0 | $85,362 | $0 | 08/24/2018 | F - Formal Settlement |