Inspection: 1202183 - Griffin Foundry And Manufacturing Co.
Inspection Information - Office: Atlanta East Area Office
Site Address:
Griffin Foundry And Manufacturing Co.
210 Decatur Street
Rome, GA 30161
Mailing Address:
P.O. Box 224, Rome, GA 30161
Union Status: NonUnion
SIC:3321
NAICS: 0
Inspection Type: Planned
Scope: Complete
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 05/08/1985
Planning Guide: Safety-Manufacturing
Emphasis:
Case Closed: 01/06/1986
| Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
|---|---|---|---|---|---|---|
| Initial Violations | 1 | 1 | 2 | |||
| Current Violations | 1 | 1 | 2 | |||
| Initial Penalty | $240 | $0 | $0 | $0 | $0 | $240 |
| Current Penalty | $130 | $0 | $0 | $0 | $0 | $130 |
| FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
| # | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1. | 01001A | Serious | 19100215 A01 | 04/01/1985 | 05/06/1985 | $130 | $240 | $0 | 04/15/1985 | J - ALJ Decision | |
| 2. | 01001B | Serious | 19100215 A04 | 04/01/1985 | 05/06/1985 | $0 | $0 | $0 | 04/19/1985 | - | |
| 3. | 01001C | Serious | 19100215 B09 | 04/01/1985 | 05/06/1985 | $0 | $0 | $0 | 04/19/1985 | - | |
| 4. | 01001D | Serious | 19100215 B01 | 04/01/1985 | 05/06/1985 | $0 | $0 | $0 | 04/19/1985 | - | |
| 5. | 02001 | Other | 19100307 C | 04/01/1985 | 05/06/1985 | $0 | $0 | $0 | 04/19/1985 | - |