Inspection Detail
Inspection: 113891774 - Lasley Construction Inc.
Inspection Information - Office: Saint Louis Area Office
Site Address:
Lasley Construction Inc.
Bank Of Missouri
Cape Girardeau, MO 63702
Mailing Address:
3610 Lick Creek Road, Anna, IL 62906
Union Status: Union
SIC:1791
NAICS: 0
Inspection Type: Planned
Scope: Complete
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 03/03/1999
Planning Guide: Safety-Construction
Emphasis:
Case Closed: 10/14/1999
| Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
|---|---|---|---|---|---|---|
| Initial Violations | 3 | 1 | 4 | |||
| Current Violations | 4 | 4 | ||||
| Initial Penalty | $6,000 | $0 | $15,000 | $0 | $0 | $21,000 |
| Current Penalty | $6,000 | $0 | $0 | $0 | $0 | $6,000 |
| FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
| # | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1. | 01001 | Serious | 19260021 B02 | 04/19/1999 | 04/29/1999 | $1,500 | $1,500 | $0 | 05/10/1999 | F - Formal Settlement | |
| 2. | 01002 | Serious | 19261051 A | 04/19/1999 | 04/29/1999 | $1,500 | $3,000 | $0 | 05/10/1999 | F - Formal Settlement | |
| 3. | 01003A | Serious | 19261053 B13 | 04/19/1999 | 04/29/1999 | $1,500 | $1,500 | $0 | 05/10/1999 | F - Formal Settlement | |
| 4. | 01003B | Serious | 19261060 A01 III | 04/19/1999 | 04/29/1999 | $0 | $0 | $0 | 05/10/1999 | F - Formal Settlement | |
| 5. | 02001 | Serious | 19260501 B01 | 04/19/1999 | 04/29/1999 | $1,500 | $15,000 | $0 | 05/10/1999 | F - Formal Settlement |