Inspection Detail
Inspection: 103598348 - Reaction Company
Inspection Information - Office: San Francisco Ro
Site Address:
Reaction Company
Mcdonald Rt. 16
Harmon, GU 96912
Mailing Address:
415 Cho Sao Antonio, Pwb 307, Tamuning, GU 96911
Union Status: NonUnion
SIC:1791
NAICS: 238220/ Plumbing, Heating, and Air-Conditioning Contractors
Inspection Type: Planned
Scope: Complete
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 07/10/2003
Planning Guide: Safety-Construction
Emphasis: L:Progcon, S:Construction
Case Closed: 03/24/2004
| Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
|---|---|---|---|---|---|---|
| Initial Violations | 1 | 3 | 4 | |||
| Current Violations | 1 | 3 | 4 | |||
| Initial Penalty | $750 | $0 | $0 | $1,350 | $0 | $2,100 |
| Current Penalty | $750 | $0 | $0 | $0 | $0 | $750 |
| FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
| # | Citation ID | Citation Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1. | 01001 | Serious | 19260251 C05 I | 11/06/2003 | 11/20/2003 | $750 | $750 | $0 | I - Informal Settlement | ||
| 2. | 02001 | Other | 19260405 G02 III | 11/06/2003 | 11/26/2003 | $0 | $450 | $0 | I - Informal Settlement | ||
| 3. | 02002 | Other | 19260405 G02 IV | 11/06/2003 | 11/26/2003 | $0 | $450 | $0 | I - Informal Settlement | ||
| 4. | 02003 | Other | 19261051 A | 11/06/2003 | 11/20/2003 | $0 | $450 | $0 | I - Informal Settlement |