Violation Detail
Standard Cited: 19100305 B02 I Wiring methods, components, and equipment for general use.
Inspection Nr: 1510477.015
Citation: 03003
Citation Type: Other
Abatement Date: 09/06/2022 2
Initial Penalty: $1,205.00
Current Penalty: $1,000.00
Issuance Date: 07/15/2021
Nr Instances: 2
Nr Exposed: 15
Related Event Code (REC):
Gravity:
Report ID: 0627500
Contest Date: 08/04/2021
Final Order: 03/04/2022
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 03/04/2022 | $1,000.00 | 09/06/2022 | Other | |
Penalty | C: Contested | 08/09/2021 | $1,205.00 | 07/27/2021 | Other | |
Penalty | Z: Issued | 07/15/2021 | $1,205.00 | 07/27/2021 | Other |
Text For Citation: 03 Item/Group: 003 Hazard:
29 CFR 1910.305(b)(2)(i): Pull boxes, junction boxes, and fittings were not provided with covers approved for the purpose: On or about February 24, 2021, junction and outlet boxes did not have a cover or faceplate, exposing employees to electrical hazards in the following instances: 1) On the east wall, two 277/480V circuit breaker panels were missing their panel covers. 2) Behind 600 Ton CMC Clearing Mechanical Press #112 (Serial # S4-600-1080-72, Model# S1-17261P) and near the south wall, the Chiller was missing its side and front panels.