Violation Detail
Standard Cited: 19100212 A04 General requirements for all machines.
Inspection Nr: 1401254.015
Citation: 01009
Citation Type: Serious
Abatement Date: 12/13/2019 2
Initial Penalty: $9,282.00
Current Penalty: $2,000.00
Issuance Date: 11/08/2019
Nr Instances: 2
Nr Exposed: 5
Related Event Code (REC):
Gravity: 10
Report ID: 0936400
Contest Date:
Final Order: 12/26/2019
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 12/26/2019 | $2,000.00 | 12/13/2019 | Serious | |
Penalty | Z: Issued | 11/08/2019 | $9,282.00 | 12/13/2019 | Serious |
Text For Citation: 01 Item/Group: 009 Hazard:
29 CFR 1910.212(a)(4): Revolving drum(s), barrel(s), or container(s) were not guarded by enclosure(s) which were interlocked with the drive mechanism so that the barrel(s), drum(s), or container(s) could not revolve unless the enclosure(s) were in place: a) B Building- The first OCEM Press cement mixer did not have interlocks that engaged when the enclosure was opened, exposing employees to caught-in, amputation, and crushing hazards from moving parts b) B Building- A broken chain on the second OCEM Press cement mixer prevented the interlock from activating when the enclose was opened, exposing employees to caught-in, amputation, and crushing hazards from moving parts.