Violation Detail
Standard Cited: 19101000 E Air contaminants.
Inspection Nr: 1259737.015
Citation: 01006B
Citation Type: Serious
Abatement Date: 3
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 02/27/2018
Nr Instances: 1
Nr Exposed: 1
Related Event Code (REC): A
Gravity: 10
Report ID: 0317500
Contest Date: 03/19/2018
Final Order: 09/28/2018
Emphasis:
Substance: 1480
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | J: ALJ Decision | 09/28/2018 | $0.00 | Serious | ||
Penalty | C: Contested | 04/20/2018 | $0.00 | Serious | ||
Penalty | Z: Issued | 02/27/2018 | $0.00 | Serious |
Text For Citation: 01 Item/Group: 006B Hazard:
29 CFR 1910.1000(e): Feasible administrative or engineering controls were not determined and implemented to achieve compliance with the limits prescribed in 29 CFR 1910.1000(a) through (d): a) In the North Division Vault of the North LDS Pond, on or about August 30, 2017 - The employer failed to determine and implement feasible administrative or engineering controls to achieve compliance with the permissible exposure and ceiling limits for hydrogen sulfide while a FirstEnergy employee was working at the top of the vault and, at the same time, contractors removed an elbow from the 24-inch LDS pipe line.