Violation Detail
Standard Cited: 19100184 E03 I Slings.
Inspection Nr: 1118265.015
Citation: 01013B
Citation Type: Serious
Abatement Date: 07/14/2016 2
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 07/08/2016
Nr Instances: 5
Nr Exposed: 200
Related Event Code (REC):
Gravity: 10
Report ID: 0625400
Contest Date:
Final Order: 07/29/2016
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 07/29/2016 | $0.00 | 07/14/2016 | Serious | |
Penalty | Z: Issued | 07/08/2016 | $0.00 | 07/14/2016 | Serious |
Text For Citation: 01 Item/Group: 013B Hazard:
29 CFR 1910.184(e)(3)(i): A thorough periodic inspection of alloy steel chain slings was not made on a regular basis and/or were done at intervals greater than once every 12 months. On or about 13 January 2016 and at times prior thereto, the employer failed to conduct a thorough periodic inspection of alloy steel chain slings within the last 12 months, exposing employees to the hazard of being struck by falling loads.