Standard Cited: 19100147 C06 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1008154.015
Citation: 01002A
Citation Type: Serious
Abatement Date: 05/29/2015 2
Initial Penalty: $5,000.00
Current Penalty: $2,500.00
Issuance Date: 01/08/2015
Nr Instances: 1
Nr Exposed: 7
Related Event Code (REC): C
Gravity: 5
Report ID: 0112600
Contest Date:
Final Order: 02/04/2015
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | P: Petition to Mod Abatement | $2,500.00 | 05/29/2015 | Serious | ||
Penalty | I: Informal Settlement | 02/04/2015 | $2,500.00 | 02/04/2015 | Serious | |
Penalty | Z: Issued | 01/08/2015 | $5,000.00 | 02/04/2015 | Serious |
Text For Citation: 01 Item/Group: 002A Hazard:
29 CFR 1910.147(c)(6)(i): The employer did not conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirement of this standard were being followed: Porter and Chester, 1984 Westover Road, Chicopee, Massachusetts; The employer did not conduct periodic inspections of the energy control procedures at least annually by an authorized employee to ensure that the procedures met the requirements of 29 CFR 1910.147 and were being followed for locking out equipment regularly locked out in the HVACR and electrical labs.