Standard Cited: 19100303 F02 General.
Inspection Nr: 1331740.015
Citation: 04001
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 10/12/2018
Nr Instances: 2
Nr Exposed: 10
Abatement Date: 11/07/2018
Gravity:
Report ID: 0418100
Contest Date: 11/05/2018
Final Order: 06/19/2019
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 06/19/2019 | $0.00 | 11/07/2018 | Other | |
Penalty | C: Contested | 11/09/2018 | $0.00 | 11/07/2018 | Other | |
Penalty | Z: Issued | 10/12/2018 | $0.00 | 11/07/2018 | Other |
Text For Citation: 04 Item/Group: 001 Hazard:
29 CFR 1910.303(f)(2): Each service, feeder, and branch circuit, at its disconnecting means or overcurrent device, was not legibly marked to indicate its purpose, nor located and arranged so the purpose was evident: a) On or about July 20, 2018 and times prior to, at the electrical panel next to the office where employees used the panel box to turn on and off the lighting and compressors. The panel box had some breakers that were not labeled or the handwriting was illegible. b) On or about July 20, 2018 and times prior to, at the workshop where employees used the panel box to turn on and off the lighting and compressors. The panel box had breakers that were not labeled or the handwriting was illegible.