Violation Detail
Standard Cited: 19100303 B02 General.
Inspection Nr: 1119628.015
Citation: 03007A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $5,000.00
Current Penalty: $5,000.00
Issuance Date: 07/13/2016
Nr Instances: 6
Nr Exposed: 12
Abatement Date: 08/29/2016
Gravity: 5
Report ID: 0112000
Contest Date: 08/04/2016
Final Order: 04/17/2017
Related Event Code (REC): C
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 04/17/2017 | $5,000.00 | 08/29/2016 | Serious | |
Penalty | C: Contested | 08/05/2016 | $5,000.00 | 08/29/2016 | Serious | |
Penalty | Z: Issued | 07/13/2016 | $5,000.00 | 08/29/2016 | Serious |
Text For Citation: 03 Item/Group: 007A Hazard:
29 CFR 1910.303(b)(2): Listed or labeled electrical equipment was not used or installed in accordance with instructions included in the listing or labeling: A. Warehouse, UPS Table: On, or about, January 27, 2016, a scale was energized through a relocatable power tap that was energized through another relocatable power tap. B. Coater 4: On, or about, February 3, 2016, a knockout box designed for permanent wiring was used in an extension cord assembly to energize a Graco displacement pump. C. Mezzanine Electrical Room: 1. On, or about, January 15, 2016, Square D 120/240 volt panelboard identified as Coater #2 Control Power: The box was mounted on shop-made standoff's. 2. On, or about, January 15, 2016, Square D 120/240 volt panelboard identified as Coater 1 Power Distribution: The box was mounted on shop-made standoff's. 3. On, or about, January 15, 2016, Square D disconnect switch labeled as Pilot Coater Main Disconnect: The handle provided on the switch had been taken off discarded electrical equipment and was welded onto the lever mechanism. According to the manufacturer, the modification of the switch was not in accordance with instructions or listing for the equipment. 4. On, or about, January 15, 2016, Square D I-Line panelboards installed for power distribution for Coating Lines #1, #2 and #3: Each panelboard assembly was not installed with the enclosure that was provided by the manufacturer.