Violation Detail
Standard Cited: 19100303 F02 General.
Inspection Nr: 1542164.015
Citation: 03005
Citation Type: Other
Abatement Date: 3
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 01/06/2022
Nr Instances: 3
Nr Exposed: 4
Related Event Code (REC):
Gravity:
Report ID: 0112000
Contest Date:
Final Order: 02/11/2022
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 02/11/2022 | $0.00 | Other | ||
Penalty | Z: Issued | 01/06/2022 | $0.00 | Other |
Text For Citation: 03 Item/Group: 005 Hazard:
29 CFR 1910.303(f)(2):Each service, feeder, and branch circuit, at its disconnecting means or overcurrent device, was not legibly marked to indicate its purpose, nor located and arranged so the purpose was evident: A. Plastics Department, Work Area of Negri Bossi H1600 Horizontal Injection Molding Machine: On, or about, July 28, 2021, the electrical disconnect for the machine was not labelled to indicate its purpose. B. Metal Department, Tumbling Area: On, or about, August 6, 2021, two ITE disconnect boxes provided for vibratory bowls were not labelled.