Violation Detail
Standard Cited: 19100147 C06 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1519954.015
Citation: 03003
Citation Type: Other
Abatement Date: 08/17/2021
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 07/22/2021
Nr Instances: 1
Nr Exposed: 4
Related Event Code (REC):
Gravity:
Report ID: 0215800
Contest Date: 08/12/2021
Final Order:
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | C: Contested | 08/12/2021 | $0.00 | 08/17/2021 | Other | |
Penalty | Z: Issued | 07/22/2021 | $0.00 | 08/17/2021 | Other |
Text For Citation: 03 Item/Group: 003 Hazard:
29 CFR 1910.147(c)(6)(i):The employer did not conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirement of this standard were being followed: (a) On or about 3/23/2021, the last periodic inspection of the company's energy control procedures was conducted during August of 2018.