Violation Detail
Standard Cited: 19100147 C06 II The control of hazardous energy (lockout/tagout).
Inspection Nr: 1710347.015
Citation: 03002
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $1,423.00
Current Penalty: $803.50
Issuance Date: 03/29/2024
Nr Instances: 1
Nr Exposed: 4
Abatement Date: 10/28/2024
Gravity:
Report ID: 0134000
Contest Date: 04/29/2024
Final Order: 11/18/2024
Related Event Code (REC): R
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 11/18/2024 | $803.50 | 10/28/2024 | Other | |
| Penalty | C: Contested | 05/01/2024 | $1,423.00 | 04/24/2024 | Other | |
| Penalty | Z: Issued | 03/29/2024 | $1,423.00 | 04/24/2024 | Other |
Text For Citation: 03 Item/Group: 002 Hazard:
29 CFR 1910.147(c)(6)(ii) - The employer did not certify that periodic inspections of the energy control procedures had been performed: Location - Production Floor On or about 11/14/2023, periodic inspections of the energy control procedures developed for the Fedco Model PD414 Hopper had not been certified.