Violation Detail
Standard Cited: 19100107 B05 I Spray finishing using flammable and combustible materials.
Inspection Nr: 1640211.015
Citation: 03002
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 06/16/2023
Nr Instances: 1
Nr Exposed: 3
Abatement Date: 07/07/2023
Gravity:
Report ID: 0214500
Contest Date: 06/22/2023
Final Order: 04/22/2024
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | J: ALJ Decision | 04/22/2024 | $0.00 | 07/07/2023 | Other | |
Penalty | C: Contested | 06/30/2023 | $0.00 | 07/07/2023 | Other | |
Penalty | Z: Issued | 06/16/2023 | $0.00 | 07/07/2023 | Other |
Text For Citation: 03 Item/Group: 002 Hazard:
29 CFR 1910.107(b)(5)(i):The average air speed over the open face of the paint spray booth was less than 100 linear feet per minute: a) Spray Finishing Shop: Employees were required to conduct spray finishing inside an open face booth and the air speed over the face of the booth measured 96 linear feet per minute. The employer did not ensure that the average air speed across the face of the open face spray painting booth was less than 100 linear feet per minute, on or about 12/21/22.