Violation Detail
Standard Cited: 19261417 O01
Inspection Nr: 1657907.015
Citation: 03001E
Citation Type: Willful
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 09/15/2023
Nr Instances: 5
Nr Exposed: 4
Abatement Date: 12/18/2023
Gravity: 10
Report ID: 0134000
Contest Date:
Final Order: 12/01/2023
Related Event Code (REC): R
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 12/01/2023 | $0.00 | 12/18/2023 | Willful | |
Penalty | Z: Issued | 09/15/2023 | $0.00 | 12/18/2023 | Willful |
Text For Citation: 03 Item/Group: 001E Hazard:
29 CFR 1926.1417(o)(1): The equipment was operated in excess of its rated capacity. Location: 25 Sixth Street, Chelsea, MA; On or about 03/21/2023, the Tadano GR800XL (serial number: 547134) crane was operated multiple times outside of acceptable limits as stated on the load charts in the operators cab which called for the counterweight to be installed and was logged on the equipment's LMI/AML.