Violation Detail
Standard Cited: 19100147 C04 II A The control of hazardous energy (lockout/tagout).
Inspection Nr: 1710347.015
Citation: 03001
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $1,423.00
Current Penalty: $803.50
Issuance Date: 03/29/2024
Nr Instances: 1
Nr Exposed: 4
Abatement Date: 10/28/2024
Gravity:
Report ID: 0134000
Contest Date: 04/29/2024
Final Order: 11/18/2024
Related Event Code (REC): R
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 11/18/2024 | $803.50 | 10/28/2024 | Other | |
Penalty | C: Contested | 05/01/2024 | $1,423.00 | 04/24/2024 | Other | |
Penalty | Z: Issued | 03/29/2024 | $1,423.00 | 04/24/2024 | Other |
Text For Citation: 03 Item/Group: 001 Hazard:
29 CFR 1910.147(c)(4)(ii)(A) - The energy control procedures did not contain a specific statement on the intended use of the procedure: Location - Production Area On or about 11/14/23, the written Lockout Tagout procedure for the Fedco Model PD414 Hopper did not include a statement regarding the intended use of the procedure