Violation Detail
Standard Cited: 19030019 C01 Abatement verification.
Inspection Nr: 1511017.015
Citation: 03001
Citation Type: Other
Abatement Status: Not Completed - AD Discretion
Initial Penalty: $329.00
Current Penalty: $329.00
Issuance Date: 10/19/2021
Nr Instances: 2
Nr Exposed: 3
Abatement Date: 11/01/2021
Gravity:
Report ID: 0522300
Contest Date:
Final Order: 11/17/2021
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | Z: Issued | 10/19/2021 | $329.00 | 11/01/2021 | Other |
Text For Citation: 03 Item/Group: 001 Hazard:
29 CFR 1903.19(c)(1):The employer did not certify to OSHA, within 10 calendar days after the abatement date, that the cited violation had been abated: Items requiring certification: a) Failed to provide abatement verification documentation for Citation No. 1 Item. Each employee engaged in residential construction activities 6 feet (1.8 m) or more above lower levels shall be protected by guardrail systems, safety net system, or personal fall arrest system unless another provision in paragraph (b) of this section provides for an alternative fall protection measure. b) Failed to provide abatement verification documentation for Citation No. 1 Item. The employer shall ensure that each affected employee uses eye protection that provides side protection when there is a hazard from flying objects. Detachable side protectors (e.g. clip-on or slide-on side shields) meeting the pertinent requirements of this section are acceptable.