Violation Detail
Standard Cited: 19040040 A
Inspection Nr: 1268292.015
Citation: 03001
Citation Type: Other
Abatement Status: Not Completed - Worksite Changed
Initial Penalty: $1,423.00
Current Penalty: $2,500.00
Issuance Date: 04/03/2018
Nr Instances: 2
Nr Exposed: 45
Abatement Date: 04/17/2018
Gravity:
Report ID: 0521400
Contest Date: 04/09/2018
Final Order: 01/22/2019
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 01/22/2019 | $2,500.00 | 04/17/2018 | Other | |
Penalty | C: Contested | 04/10/2018 | $1,423.00 | 04/17/2018 | Other | |
Penalty | Z: Issued | 04/03/2018 | $1,423.00 | 04/17/2018 | Other |
Text For Citation: 03 Item/Group: 001 Hazard:
29 CFR 1904.40(a): Basic requirement. When an authorized government representative asks for the records you keep under Part 1904, you must provide copies of the records within four (4) business hours. a. On or about October 05, 2017 at 1514 23rd Ave, Rockford, IL 61104, documents were requested during opening conference. The employer failed to respond to said request within four hours. b. On or about October 10, 2017 a written document request was delivered to Baney Construction Inc. with a response required by October 18, 2017. The employer failed to reply to this request. Abatement documentation is required of this item in accordance with the requirements of 29 CFR 1903.19(d).