Standard Cited: 19260405 G02 III Wiring methods, components, and equipment for general use.

Inspection Nr: 1246617.015

Citation: 03001

Citation Type: Other

Abatement Status: Abatement Completed

Initial Penalty: $0.00

Current Penalty: $0.00

Issuance Date: 09/15/2017

Nr Instances: 1

Nr Exposed: 1

Abatement Date: 09/21/2017

Gravity:

Report ID: 0316100

Contest Date:

Final Order: 11/15/2017

Related Event Code (REC):

Emphasis:


Penalty and Failure to Abate Event History
Type Latest Event Event Date Penalty Abatement Due Date Citation Type Failure to Abate Inspection
Penalty Z: Issued 09/15/2017 $0.00 09/21/2017 Other  

Text For Citation: 03 Item/Group: 001 Hazard:

29 CFR 1926.405(g)(2)(iii): Flexible cords were not used in continuous lengths without splice or tap: a) Fourth Floor - An employee was using a Milwaukee 7 1/4" portable electric saw to cut wood framing members and the cord had been severed and spliced, 120 volt 15 amp service, on or about 07/13/2017. In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the Certification of Corrective Action Worksheet).

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.