Violation Detail
Standard Cited: 19100303 G01 I A General.
Inspection Nr: 1542164.015
Citation: 02033A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $4,096.00
Current Penalty: $3,000.00
Issuance Date: 01/06/2022
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 02/24/2022
Gravity: 1
Report ID: 0112000
Contest Date:
Final Order: 02/11/2022
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 02/11/2022 | $3,000.00 | 02/24/2022 | Serious | |
Penalty | Z: Issued | 01/06/2022 | $4,096.00 | 02/24/2022 | Serious |
Text For Citation: 02 Item/Group: 033A Hazard:
29 CFR 1910.303(g)(1)(i)(A): For electric equipment operating at 600 volts, nominal, or less to ground, and likely to require examination, adjustment, servicing, or maintenance while energized, the depth of the working space in the direction of access to live parts (as measured from the live parts where they were exposed or from the enclosure front or opening where they were enclosed) was less than indicated in Table S-1 of Subpart S of Part 1910: Plastics Finishing: On, or about, August 27, 2021, a Hobart forktruck charging unit and a bench mounted finishing machine were located in the working space in front of a General Electric circuit breaker panel labeled "Power" and a panelboard that energized presses in the area.