Violation Detail
Standard Cited: 19100119 D03 II Process safety management of highly hazardous chemicals.
This violation item has been deleted.
Inspection Nr: 311611081
Citation: 02020A
Citation Type: Willful
Abatement Status:
Initial Penalty: $70,000.00
Current Penalty: $0.00
Issuance Date: 03/08/2010
Nr Instances: 1
Nr Exposed: 25
Abatement Date: 04/19/2010
Gravity: 10
Report ID: 0524700
Contest Date: 03/31/2010
Final Order: 09/27/2018
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | R: Review Commission | 09/27/2018 | $0.00 | Willful | ||
Penalty | Z: Issued | 03/08/2010 | $70,000.00 | Willful |
Text For Citation: 02 Item/Group: 020A Hazard: REFINERY
29 CFR 1910.119(d)(3)(ii): The employer does not document that the equipment in the process complies with recognized and generally accepted good engineering pra ctices: a.BP-Husky Refining, LLC - Oregon, Ohio: The employer does not document the need for over pressure protection on pressure vessels as required by recogni zed and generally accepted good engineering practices. The Lower Pumparound Cool er (PR543757) is not protected by pressure relieving devices that would prevent the pressure inside the vessel from rising above acceptable limits. Pursuant to 29 CFR 1903.19, within ten (10) calendar days of the abatement date, the employe r must submit documentation that it has abated the hazard. In addition, under 29 CFR 1903.19(e), the employer must submit an abatement plan describing the actio ns it is taking to ensure that it is in compliance with the standards for all pr essure vessels, including documenting that each pressure vessel has been evaluat ed and is protected by pressure-relieving device(s) in accordance with recognized and generally accepted good engineering practices, such as the ASME Boiler and Pressure Vessel Code. The abatement plan shall esta blish dates during the next three months when the evaluations and installations of overpressure protection shall be completed. Once the plan has been fully impl emented, the employer must submit certification of its full compliance with the standard.