Violation Detail
Standard Cited: 19100119 D03 II Process safety management of highly hazardous chemicals.
This violation item has been deleted.
Inspection Nr: 311611081
Citation: 02016A
Citation Type: Willful
Abatement Status:
Initial Penalty: $70,000.00
Current Penalty: $0.00
Issuance Date: 03/08/2010
Nr Instances: 1
Nr Exposed: 25
Abatement Date: 04/19/2010
Gravity: 10
Report ID: 0524700
Contest Date: 03/31/2010
Final Order: 09/27/2018
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | R: Review Commission | 09/27/2018 | $0.00 | Willful | ||
Penalty | Z: Issued | 03/08/2010 | $70,000.00 | Willful |
Text For Citation: 02 Item/Group: 016A Hazard: REFINERY
29 CFR 1910.119(d)(3)(ii): The employer does not document that the equipment in the process complies with recognized and generally accepted good engineering pra ctices: a.BP-Husky Refining, LLC - Oregon, Ohio: The employer does not document compliance with recognized and generally accepted good engineering practices by ensuring PSV- 1280, a conventional relief valve, has a back pressure of less tha n or equal to 10of its set pressure. This relief device provides protection to t he FCC Feed Drum, and relieves hydrocarbons to the flare. Pursuant to 29 CFR 190 3.19, within ten (10) calendar days of the abatement date, the employer must submit documentation that it has abated the hazard. In addition, under 29 C FR 1903.19(e), the employer shall submit an abatement plan describing the action s it is taking to ensure that it is in compliance with the standards including d ocumentation that each pressure relief valve and associated piping for all proce ss units have been evaluated and, if necessary, repaired or replaced to ensure b ackpressure is limited in accordance with recognized and generally accepted good engineering practices, such as API Recommended Practice 520/521 and the ASME Bo iler and Pressure Vessel Code. The abatement plan shall establish dates during t he next three months when the evaluations, repairs, and replacements shall be co mpleted. Once the plan has been fully implemented, the employer must submit cert ification of its full compliance with the standard.