Violation Detail
Standard Cited: 19100304 G05 Wiring design and protection.
Inspection Nr: 314767104
Citation: 02011
Citation Type: Other
Abatement Date: 03/31/2011 X
Initial Penalty: $1,000.00
Current Penalty: $1,000.00
Issuance Date: 03/14/2011
Nr Instances: 2
Nr Exposed: 12
Related Event Code (REC):
Gravity: 03
Report ID: 0625700
Contest Date: 04/04/2011
Final Order: 04/11/2012
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | Z: Issued | 03/14/2011 | $1,000.00 | Other |
Text For Citation: 02 Item/Group: 011 Hazard: REFINERY
29 CFR 1910.304(g)(5): The path to ground from circuits, equipment, and enclosur es was not permanent and continuous: a) The employer does not ensure adequate pa th to ground for electrical equipment. A ground prong was missing from a 30 inch pedestal fan. This violation was observed on or about September 22, 2010 in the maintenance shop. b) The employer does not ensure adequate path to ground for e lectrical equipment. A ground prong was missing from a 4 foot by 4 foot portable box fan. This violation was observed on or about September 22, 2010 in the main tenance shop. Pursuant to 29 C.F.R. 1903.19, within ten (10) calendar days of th e date of this citation, the employer must submit documentation showing that it is in compliance with the standard, including the steps that it is taking to ensure that employees are not being exp osed to electrical hazards.