Violation Detail
Standard Cited: 19101001 K01 Asbestos.
Inspection Nr: 1651629.015
Citation: 02007
Citation Type: Other
Abatement Status: Corrected During Inspection
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 05/19/2023
Nr Instances: 1
Nr Exposed: 4
Abatement Date:
Gravity:
Report ID: 0112000
Contest Date:
Final Order: 07/06/2023
Related Event Code (REC):
Emphasis:
Substance: 9020
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 07/06/2023 | $0.00 | Other | ||
Penalty | Z: Issued | 05/19/2023 | $0.00 | Other |
Text For Citation: 02 Item/Group: 007 Hazard:
29 CFR 1910.1001(k)(1): All surfaces were not maintained as free as practicable of ACM waste and debris and accompanying dust: First Floor Raw Material Storage: On, or about, February 17, 2023, pipe insulation that contained asbestos had deteriorated and/or been struck by material handling equipment causing pieces of the material to fall onto the floor. The insulation had not been cleaned and repaired.