Violation Detail
Standard Cited: 19100304 G05 Wiring design and protection.
Inspection Nr: 1764494.015
Citation: 02005
Citation Type: Other
Abatement Status: Corrected During Inspection
Initial Penalty: $16,131.00
Current Penalty: $8,065.00
Issuance Date: 01/15/2025
Nr Instances: 2
Nr Exposed: 6
Abatement Date:
Gravity: 10
Report ID: 0627100
Contest Date:
Final Order: 02/04/2025
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 02/04/2025 | $8,065.00 | Other | ||
Penalty | Z: Issued | 01/15/2025 | $16,131.00 | Serious |
Text For Citation: 02 Item/Group: 005 Hazard:
29 CFR 1910.304(g)(5): The path to ground from circuits, equipment, and enclosures was not permanent, continuous, and effective: On or about July 24, 2024, on the A-Line, employees were performing continuous vulcanizing, where the grounding prong was interrupting the equipment's path to ground in that: a) Two Profitter drum fans were missing ground pins. b) One Profitter drum fan was plugged into the outlet upside down.