Violation Detail
Standard Cited: 19100305 B02 I Wiring methods, components, and equipment for general use.
Inspection Nr: 1659692.015
Citation: 02005
Citation Type: Other
Abatement Status: Corrected During Inspection
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 05/19/2023
Nr Instances: 1
Nr Exposed: 2
Abatement Date:
Gravity:
Report ID: 0112000
Contest Date:
Final Order: 05/30/2023
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 05/30/2023 | $0.00 | Other | ||
| Penalty | Z: Issued | 05/19/2023 | $0.00 | Other |
Text For Citation: 02 Item/Group: 005 Hazard:
29 CFR 1910.305(b)(2)(i): Pull boxes, junction boxes, and fittings were not provided with covers approved for the purpose: Basement, Mechanical Room: On, or about, March 9, 2023, a junction box provided to energize a circulator pump was not provided with a cover.